Route 1 & Telegraph Rd/Woodstock Ln Improvements


Jefferson Davis Highway (US-1) from Telegraph Road to Woodstock Lane Safety Improvements

telegraph roadPurpose

This project seeks to improve the safety of two sequential intersections, Telegraph Road (Route 637) and Woodstock Lane (Route 639) along a portion of Jefferson Davis Highway (US-1). The project will realign the intersection of US-1 and Telegraph Road to eliminate the skewed intersection and install a permanent traffic signal. The intersection with Woodstock Lane will be channelized, eliminating left turns exiting Woodstock Lane onto US-1 southbound. In order to travel southbound on US-1, traffic will have to utilize the new traffic signal at Telegraph Road



Update- December 2019

Public Hearing was held on Wednesday, November 20, 2019 Public Notice

Schedule

  • Design work submitted to VDOT for approval
  • Anticipate starting right-of-way acquisition process in winter/spring 2020
  • Anticipate starting private utility relocations in summer 2021 
  • Anticipate starting construction in spring 2022
  • Anticipate project completion in winter 2022

Cost 

County/Transportation Fund = $1,275,200

VDOT SMART SCALE Fund = $7,524,800

Project Contacts

Project Manager: Nate Huber, P.E. (540) 658-5199

Transportation Project Manager: Alex Owsiak, P.E. (540) 658-4593


Stafford County ensures nondiscrimination in all programs and activities in accordance with Title VI of the Civil Rights Act of 1964