Berea Church Road Improvements

STATE ROUTE 654

2017-12-14 Berea Church Rd Brochure DRAFT

PURPOSE

To provide roadway safety improvements from Warrenton Road (US-17) to Truslow Road (SR-652).  The project includes vertical profile and horizontal improvements for ride and safety.  Drainage will be improved with new roadway ditches, culverts, and stormwater management swales.  

UPDATE - SEPTEMBER 2019

 Addressing VDOT comments on Right-of-Way plan submission
 Working with private utilitycompanies (Dominion, Verizon, etc.) to identify their relocations and easements

SCHEDULE  

Anticipate starting Right-of-WayAcquisition process in Fall 2019

Anticipate starting Utilityrelocations in Summer 2020

Anticipate starting Constructionin Spring 2021

Public Hearing - June 14, 2018 Brochure

COST  (Estimated)

  • $6.1 M - Including design costs, right-of-way acquisition, utility relocations, construction, and inspections.

CONTACT