Berea Church Road Improvements

STATE ROUTE 654

2017-12-14 Berea Church Rd Brochure DRAFT

PURPOSE

To provide roadway safety improvements from Warrenton Road (US-17) to Truslow Road (SR-652).  The project includes vertical profile and horizontal improvements for ride and safety.  Drainage will be improved with new roadway ditches, culverts, and stormwater management swales.  

UPDATE - MAY 2019

•    Project will require Right-of-Way acquisition from approximately 28 parcels

SCHEDULE  

  • Anticipate Right-of-Way plans submitted to VDOT and under review
  • Anticipate starting Right-of-Way Acquisition process in June 2019
  • Anticipate starting Utility Relocations in Fall 2019
  • Anticipate Construction in Fall 2020
  • Final Design completed Fall 2018
  • Citizen Information Meeting held - December 14, 2017

Public Hearing - June 14, 2018 Brochure

COST  (Estimated)

  • $6.5 M - Other project costs not quantified include costs for right-of-way acquisition, inspections and testing during construction.