PURPOSE

To provide roadway safety improvements from Warrenton Road (US-17) to Truslow Road (SR-652).  The project includes vertical profile and horizontal improvements for ride and safety.  Drainage will be improved with new roadway ditches, culverts, and stormwater management swales.  

UPDATE - JUNE 2019

•    Right-of-Way plans submitted to VDOT for review - Working with private utility companies to identify their relocations

SCHEDULE  

  • Anticipate starting Right-of-Way Acquisition process August 2019
  • Anticipate starting Utility Relocations Spring 2020
  • Anticipate starting Construction Spring 2021

Public Hearing - June 14, 2018 Brochure

COST  (Estimated)

  • $6.1 M - Including design costs, right-of-way acquisition, utility relocations, construction, and inspections.