The US-1 (Jefferson Davis Highway) & Courthouse Road (SR-630) Intersection Improvement Project will widen approximately 0.65 miles of Route 1 to provide dedicated left-turn lanes onto Courthouse Road and Bells Hill (SR-631) / Hope Road (SR-687).  US-1 will be improved to a 4-lane, divided roadway with a concrete median separating northbound and southbound traffic.  Dedicated left-turn lanes will be added to US-1 at Courthouse Road and the Bells Hill/Hope Road intersection to improve traffic signal function and reduce intersection delays.  Eastbound Courthouse Road will be widened to provide a dedicated left-turn, right-turn, and through lane. Westbound Courthouse Road will be re-striped to provide a dedicated left-turn, right-turn, and through lane.  An 8 foot sidewalk will also be installed along both sides of US-1.

UPDATE  FEBRUARY 2019 

•    Project will require Right-of-Way Acquisition from 29 parcels

•    All Purchase Offers have been delivered to Property Owners

•    5 Purchase Offers have been accepted

•    Currently working with impacted Property Owners to address their concerns

TIMELINE  

  • Completion of Property Appraisals January 2019
  • Anticipate starting Utility Relocations in Spring 2019 
  • Construction starting in early 2020 
  • Completion by end of 2021

Public Hearing Brochure - June 9, 2016

CONTACT

Alex Owsiak,  PE - Transportation Project Manager - (540) 658-4593 - AOwsiak@staffordcountyva.gov